Construction at ETAA

Great things are happening at Ezequiel Tafoya Alvarado Academy. As we continue to grow and provide excellent programs and services to our students, we must also focus on building and expanding our facilities here on campus as well. Thanks to a grant we received over 3 years for $1.5 million dollars, our vision is possible. 

Below is a timeline of when we expect to have the different phases of construction completed.

2016-2017

PHASE 1
  • December: Playing Field/Restrooms/Storage/Snack Bar
  • November - February: Offices
https://sites.google.com/a/etaacharter.com/main/parent-info/construction-at-etaa/20161125_092548.jpg   

PHASE 2
  • February - August: Northern Classroom Wing (12 Classrooms and Library/Restrooms) 

2017-2018

PHASE 3
  • August - January: Gymnasium/Parking
PHASE 4
  • January - August: Western Classroom Wing (12 Classrooms)

2018-2019

PHASE 5
  • 5 Classroom Wing
  • Band Hall
  • Art Room
  • Technology Building
  • Natural Science
  • Restrooms
Classroom Phase I


Classroom Phase II

Office and Snack Bar Addition